This has been reported in timesofindia.indiatimes.com dated 2 November 2015.
The cost of the project has more than doubled from Rs 6,000 crore to Rs 13,800 crore and, Phase 1 of the project, covering 42-Km, was to have been opened this year but the completion date has now been pushed to the first quarter of 2016. Asa per a recent survey published in railyatri.in, it appears that Bangalore Metro Rail Corporation (BMRC) will take up to 2032 to complete both phases and provide the city with a 114-Km network.
The survey found that Bengaluru Metro had been able to construct 1.5-Km of network every year. In contrast, Delhi Metro built 8-Km per year in the first phase.
It may be recalled that when former PM Manmohan Singh had laid the foundation stone for Namma Metro in June 2006, the first line, Byappanahalli-MG Road, was to be operational by 2009 and the first phase by 2011. however, the first line was only commissioned in October 2011 - the rest of Phase 1 is still being built.
(Image courtesy wikimediacommons.org)
Some more interesting links -
The global broom campaign (satire)
Moody searching for a place where no leader has gone (Satire)
Moody, Jet Lee and missing pulses (Satire)
Fossils and eggshells of baby dinosaurs found in Gobi Desert
Parama Island flyover adds to traffic jams in Kolkata – made one-way
Future of street foods in Delhi bleak - Delhi bans cooking on roads
Arnold Schwarzenegger could play in Rajinikanth-starrer 'Enthiran 2'
Emma Roberts and her horror-comedy series "Scream Queens"
India is one of 81 countries vying for Best Foreign Film in the 88th Academy Awards
Despite US airstrikes, ISIS still makes £300-million a year from oil
Syrian gang caught trying to smuggle 20-tonnes of cannabis worth £150million into Europe
US airdrops 50-tons of ammunition for M-16s and AK-47 to Syrian fighters
No comments:
Post a Comment